Corporation Road, Primary School

Geoffrey Robinson Limited completed the full replacement of the existing lighting installation to 17 nr classrooms throughout the school.

 

Project Value

£179,188.00

Project Duration

July 2010 – September 2010

Client

Corporation Road Primary School

Corporation Road

Darlington

DL3 6AR

 

Main Contractor

Darlington Borough Council

Town hall

Feethams

Darlington

County Durham

DL1 5QT

The overall Project included the supply and installation of the following services.

 

The works comprised of the replacement of the existing lighting installation within 17Nr classrooms throughout the school, which included the supply, installation and commissioning of the lighting circuits to BS7671. Included within our scope of works was the addition of ceiling mounted smoke detectors to the existing Fire Alarm system and the lowering and moving of existing small power points and devices where clashes occurred with the suspended ceiling.

Geoffrey Robinson Limited also carried out the electrical works to the 3Nr Mechanical Boiler houses and field device installation in line with the Mechanical Specification and Drawings.

This project was delivered on time, to budget and to clients’ specification and satisfaction.

Untitled1

Sunderland Royal Hospital

Geoffrey Robinson designed this project to save the Hospital energy.

 

Project Value              £4,500,000.00

Mechanical Services           £3,800,000.00

 

Electrical Services    £700,000.00

Project Duration

September 08 to November 09

 

Client

City Hospitals Sunderland Foundation NHS Trust

Mr Peter Dunn

Engineering Manager

0191 565 6256

Peter.Dunn@chsft.nhs.uk

 

Site Address

Kayll Road

Sunderland

Tyne and Wear

SR4 7TP

The overall Project included the supply and installation of the following services.

The scheme designed by DSSR in Harrogate was for the site wide upgrade from steam to LTHW wherever possible.

Our scope of work therefore was for the removal of the old CHP engine and two of the old steam boilers and for replacement with 3 New Hovel 5.5MW LTHW dual fuel boilers and a new CHP engine.

Site wide distribution was by means of a Durotan pre-insulated pipe work system running to plate heat exchangers in each of the remote plant rooms along with all necessary controls upgrades.  All satellite plant rooms were kept live throughout the construction period meaning the hospital was never without heating and hot water.

A late addition to the contract was for the upgrade of the site wide HV & LV cables and Switchgear.

New flues, pumps controls and pipe work were provider within the Energy Centre along with a new steel gantry and walkway to access all high level equipment.

All builders work was undertaken by GRL and relevant sub-contractors.

As part of the overall scheme a new CHP engine was installed by EnerG with all pipe work flues and gas connections being undertaken by GRL.

The project was delivered on time, to budget and to clients’ specification and satisfaction.